Guys keep troweling too early on a hot pour and blaming the mix
Saw it twice last week on a driveway in Tucson, the finisher was on the slab at 45 minutes when the mix still had bleed water coming up, and he worked it in and got a crusty top. Wait til the bleed water sheens off and the finger test leaves a clean dent, even if it means a 20 minute coffee break. What's your go-to sign that it's actually ready?